Kenya targets 421MW in geothermal expansion as electricity demand rises

Kenya’s geothermal expansion is set to deliver steam equivalent to 421 megawatts (MW) by the 2029/30 financial year, as the government seeks to strengthen electricity supply and reduce reliance on imports amid rising demand.

The Ministry of Energy and Petroleum plans to drill 34 new geothermal wells and deploy a 200-megawatt-hour (MWh) Battery Energy Storage System (BESS) to help stabilise the national grid. The programme comes as Kenya Power targets an additional 1.3 million customer connections and electricity imports from Ethiopia and Uganda account for a larger share of the country’s power supply.

Electricity imports rose to 1.91 billion kilowatt-hours (kWh) in the year to June 2026, up from 1.53 billion kWh in the previous year. Their share of the national electricity mix increased to 12.19% from 10.60%, according to the Energy and Petroleum Regulatory Authority (EPRA), reflecting the growing role of regional power purchases in meeting domestic demand.

The pressure on supply has also been reflected in Kenya’s electricity reserve margin, which fell from 20.73% in January to 3.34% in June 2026, according to earlier reporting by TechTrendsKE. Peak demand reached 2,514 MW in June and 2,549 MW in July, leaving the grid with a narrower buffer against unexpected plant outages and further increases in consumption.

Kenya’s rising electricity demand puts pressure on supply

The ministry’s plan addresses a power system in which demand is growing while available generation must cover both routine consumption and sharp increases during peak hours. Kenya Power has relied on electricity imports to help meet that demand, alongside domestic generation and thermal plants that can be brought online when additional supply is required.

The import figures underline the scale of the change. The 1.91 billion kWh purchased from neighbouring countries in the year to June represented an increase of 380 million kWh, or about 24.8%, compared with the previous year. Imports provide an important source of supply, but the higher volume also makes domestic generation capacity and the efficient use of renewable electricity important parts of Kenya’s energy planning.

Geothermal already provides the largest share of Kenya’s electricity generation. It contributed 6.42 billion kWh, equivalent to 40.1% of the national mix, in the year ended June 2026, ahead of hydropower at 22.65% and wind at 12.31%, according to the figures cited in the report.

The government is seeking to build on that established geothermal base while improving the ability of the grid to use electricity generated from other renewable sources. The approach combines additional steam resources with storage that can make electricity available at times when direct generation from wind and solar is lower.

Geothermal expansion takes centre stage

The Ministry of Energy and Petroleum says the programme will drill 34 geothermal wells to raise cumulative steam production to a level equivalent to 421 MW by the 2029/30 financial year. The wells form part of a development process that begins with exploration and drilling before the steam can be used in power plants to generate electricity.

The Geothermal Development Company is central to that process. GDC explores geothermal resources, drills wells and develops steam fields, then sells the steam to independent power producers that finance, construct and operate generating plants. The arrangement separates geothermal resource development from power generation, allowing specialised developers to take responsibility for converting the steam into electricity.

Three independent power producers have established geothermal plants with a combined generation capacity of 105 MW under this model. Globeleq, OrPower Twenty-Two and Sosian Energy each operate a 35-MW plant, with Sosian beginning electricity supply in 2023 and Globeleq and OrPower Twenty-Two starting supply to Kenya Power in 2026.

The projects provide an existing example of private investment in Kenya’s geothermal sector. The African Development Bank has also backed geothermal development at Menengai through a $16.5 million loan associated with the OrPower Twenty-Two project, illustrating the role of development finance in supporting investment in new generation infrastructure.

The 421-MW target is expressed as steam equivalent, which connects the well-drilling programme to the amount of geothermal resource available for electricity generation. Expanding that resource can support additional generating capacity as power producers develop plants capable of using the steam, strengthening the contribution of geothermal electricity to Kenya’s supply.

Battery storage targets evening power demand

Alongside geothermal development, the government plans to deploy a 200-MWh Battery Energy Storage System to improve grid stability and make better use of electricity generated by wind and solar power. The system is intended to store electricity when renewable generation is available and release it later, particularly during evening periods when demand rises.

The distinction between power and stored energy is important. Megawatts measure the rate at which electricity can be supplied, while megawatt-hours measure the amount of energy stored or delivered over time. A 200-MWh battery could, for example, deliver 100 MW for two hours under an idealised operating scenario, although its actual contribution would depend on its power rating, usable capacity and operating conditions.

Solar generation declines after sunset, while wind output varies with weather conditions. When renewable generation falls as household and business consumption rises, Kenya Power may need to draw on imports or dispatch thermal plants to meet demand. Storage can reduce some of that pressure by making previously generated electricity available later.

Kenya Power has previously highlighted the operational and cost challenges associated with variable renewable generation. Its position has reinforced the importance of dependable sources such as geothermal and hydropower, alongside storage systems that can help balance changes in supply.

The battery programme therefore complements the geothermal expansion. Additional geothermal resources can support steady generation, while storage helps manage the timing of electricity from variable renewable sources. Together, the investments are intended to improve the availability of power as demand grows and the country connects more customers.

Independent power producers hold the key to new capacity

The delivery of Kenya’s geothermal expansion depends on the relationship between GDC’s steam development and the investment decisions of independent power producers. Drilling wells creates the resource required for generation, while power plants and associated grid infrastructure are needed to turn that resource into electricity delivered to consumers.

The existing Menengai projects show how the model operates, with GDC developing steam fields and private companies building plants to use the resource. The planned expansion will build on this division of responsibilities as Kenya seeks to increase domestic generation and meet rising demand.

The wider electricity programme also has implications for the cost and reliability of supply. Additional geothermal generation could reduce the need for some imported electricity and thermal generation when domestic plants are available and competitive. Battery storage could further improve the use of renewable power by moving electricity from periods of higher output to periods of stronger demand.

Kenya’s electricity strategy is consequently centred on expanding dependable domestic generation while improving the grid’s ability to accommodate renewable energy. The 34 geothermal wells, the 200-MWh storage system and the planned customer connections form part of that effort to keep supply aligned with the country’s growing electricity needs.